The Zhejiang section of Quning Railway has been fully constructed... From January to July, the completed investment rate of key construction projects in our city reached 62.1%.

Date:2019-08-23 Source:Lishui Release Author:

  At 1:18 am on August 19, with the final blast, the Anmin Tunnel of the Suining Railway Control Project was successfully and safely finished. The Anmin Tunnel is about 13.909 kilometers long. There are 2 inclined shafts and 1 exit guide. The ground spans Daotai Township of Longquan City and Anmin Township of Songyang County. The geological conditions along the railway are very complicated, with 12 faults and 9 joints belt. In addition, the surface water is relatively developed with a maximum water inflow of 79120 square every 24 hours and a maximum buried depth of around 800 meters. There are extreme conditions such as high and low temperature and high ground stress, so that the construction conditions are extremely difficult, and the safety risk is extremely high. 

  Since the construction of the Anmin Tunnel on April 20, 2016, the China Communications Tunnel Bureau Group has organized a strong team of personnel, and conduct strict management to scientifically organize the construction. It has overcome thousands of difficulties and properly handled 8 large water surges and eliminated safety accidents. After 40 months, the construction of the Anmin Tunnel was finally finished, which created favorable conditions for the Suining Railway to open operations on schedule. 

  The Anmin Tunnel is the last tunnel that runs through the Lishui section of the Quning Railway. Finishing the construction of Anmin Tunnel marks the entire operation of the Zhejiang section of the Suining Railway. In the next step, the workers of Quning Railway will speed up the construction and make every effort to achieve the goal of operating in 2020 and help the development of "big traffic" in the city.  

  In 2019, the city arranges 225 key construction projects, with an annual planned investment of 26.3 billion yuan. From January to July, the completed investment reached 16.33 billion yuan, and 62.1% of the annual planned investment will be completed, which marks an increase of 11.5 percentage points over the previous period and is 15.4 higher than the same period of last year. The constructions of a number of projects such as Chengnan Apartment, OCT, Songyang County Huangnan Reservoir and quning Railway were accelerated. The city plans to start 70 new projects in the year, and 45 projects have been started. The operating rate has reached 64.3%. A number of projects such as the Nanming Lake Bright Night Tour Landscape Lighting Project, Yinglang Fashion Entrepreneurship Park, Yunhe Lake Juxian Island Tourism Unity, has been successful started.